Camp Shelby project also earns ESA South recognition as a Top Five Scoring Contractor in the 2026 ABC North Florida Excellence in Construction Awards
Some projects are defined by what is built. Others are defined just as much by the challenges overcome along the way.
The modernization of the Equipment Concentration Site at Camp Shelby, Mississippi, was both.
ESA South is proud to announce that the project has received an Eagle Award in the 2026 Associated Builders and Contractors (ABC) North Florida (NF) Excellence in Construction Awards, along with the prestigious distinction of being a Top Five Scoring Contractor.
ABC NF’s Excellence in Construction program recognizes outstanding quality construction produced by its members and celebrates exceptional achievement across the commercial construction industry. At the national level, ABC describes Excellence in Construction as its premier project competition, recognizing the nation’s most innovative and high-quality construction projects.
For ESA South, the recognition represents more than the successful completion of a major project. It reflects the collaboration, adaptability, technical expertise and commitment to quality that carried the Camp Shelby project from aging infrastructure to a modern facility built to support the Army Reserve mission for years to come.
Modernizing Infrastructure for the Mission Ahead
Delivered through a design-build contract, the nearly 62,110-square-foot modernization encompassed multiple facilities across a 6.97-acre Equipment Concentration Site at Camp Shelby. The work included Vehicle Maintenance Shop facilities, warehouses and storage buildings, military equipment parking areas, administrative spaces, utilities and specialized maintenance systems supporting Army Reserve vehicle operations.
What began as a modernization effort quickly became an exercise in problem-solving.
Because much of the work involved existing facilities constructed decades earlier, demolition and investigation uncovered conditions that could not have been fully evaluated during design. The team encountered hazardous materials, deficient concrete floor systems, structural repairs, utility challenges and other differing site conditions, all while managing ongoing design revisions and owner-directed modifications.
One example was the Vehicle Maintenance Shop floor. After existing concrete was determined to be unsuitable for long-term maintenance and military vehicle operations, the team moved beyond localized repairs and implemented a replacement solution designed to support the facility’s future operational demands.
Throughout construction, the design-build team had to continuously evaluate conditions, develop solutions and incorporate changes into active construction operations. Significant modifications ranged from mechanical and electrical system revisions to roof replacement, communications infrastructure improvements, security-related gate modifications, erosion remediation and structural repairs.
Even procurement became an opportunity for creative problem-solving. When an electrical transformer faced an exceptionally long lead time, the team resequenced work so that construction activities not dependent on the transformer could continue, helping preserve productivity and forward progress.
Collaboration at the Center
A project of this complexity does not succeed through construction execution alone.
ESA South worked closely with design partner Dille Pollard throughout the design-build process, alongside government stakeholders, specialty contractors, commissioning professionals and field personnel to respond to changing conditions and develop practical, long-term solutions.
The collaborative nature of design-build proved particularly important as field conditions required design revisions and engineering solutions to be developed and integrated while construction was already underway. The project team coordinated engineering reviews, procurement adjustments and field activities to keep work moving without sacrificing the functionality, maintainability or long-term performance of the finished facilities.
This award reflects the collective work of the designers, builders, trade partners and stakeholders who brought the modernization to life.
Built Through the Work of an Exceptional Team
Behind every award-winning project are the people who solved the problems, coordinated the details and kept the work moving.
The Camp Shelby project required coordination across structural, mechanical, electrical, plumbing, controls, fire protection, telecommunications, civil/site work, specialty maintenance systems and commissioning. From navigating unforeseen conditions to managing complex system integration and commissioning, every member of the project team played a role in its success.
The Camp Shelby team did more than renovate buildings. They took aging infrastructure, worked through complex unforeseen conditions and delivered facilities equipped to support a critical mission well into the future.
To our Camp Shelby project team, trade partners and everyone who contributed along the way: thank you. This recognition belongs to the people who brought their expertise, persistence and commitment to the job every day.